West Conshohocken, PA

West Conshohocken, PA

Time Frame: July 2008 - April 2009

EAT was contracted to excavate and remove both unknown and known substructures and piping, MGP-impacted material, and TSCA-level PCB-impacted material from an area directly adjacent to an active natural gas facility. This project involved several different waste streams that required extensive effort to excavate, manage on-site, stockpile, transport, and dispose of at multiple different facilities.  The known/unknown substructures included a tar holder, USTs, concrete pads, timber piles, abandoned natural gas piping, and asbestos-wrapped piping. EAT excavated and removed almost 5,000 tons of MGP-impacted soil and debris, 500 tons of TSCA-level PCB-impacted soil and debris, 2,500 linear feet of piping, and shipped 180,000 gallons of water offsite that had both MGP and PCB impacts. 

Who You Choose For Clean-up Matters

See Why Companies Trust Enviro-Air Technologies

Phillipsburg, NJ

Phillipsburg, NJ

Time Frame: September 2018 - February 2019

Enviro-Air was contracted to excavate and remove contaminated soil to a depth of 48 feet below ground level. In addition, EAT was required to excavate foundry sand from a 3-acre area and use that material as backfill in the excavation. A small TSCA PCB area was excavated, transported and disposed of at a hazardous waste factility. In addition, 12,000 tons of impacted soil were shipped to a Pennsylvania landfill. After the excavation was filled with the foundry sand, it was capped, and the entire 3 acres site was restored.

Who You Choose For Clean-up Matters

See Why Companies Trust Enviro-Air Technologies

Darby, PA

Darby, PA

Time Frame: September 2017 - September 2018

Enviro-Air was contracted to remediate a former MGP site, located on both sides of Darby Creek in Darby, PA. Fifteen thousand (15,000) tons of MGP impacted soil were excavated and disposed of offsite at a treatment/disposal facility. The excavation along the creek involved the following:

    • Installation of 6,250 square feet of soldier beams and lagging to allow for the excavation of MGP-impacted soils to a depth of 23 feet below ground surface. In conjunction with the lagging, 40 tiebacks were installed.
    • Installation of a well point dewatering system, which ran 24 hours per day, seven days per week.
    • Installation and operation of a water treatment plant consisting of activated carbon, bag filters, a weir tank and an 18,000-gallon frac tank.

In addition to the 15,000 tons of MGP-impacted soil that was removed from the site, EAT also excavated a 200 foot stretch of sediment from the bottom of Darby Creek (totaling 4,000 tons). The sediment excavation required the following:

      • Installation of a PortaDam both upstream and downstream of the excavation area. Two 48” x 200’ HDPE pipes were utilized in conjunction with the PortaDam to allow Darby Creek to bypass the excavation area.
      • Installation and operation of localized sumps to minimize water in the excavation area
      • Stabilization of saturated soils with cement kiln dust

A portion of the Darby Creek sediment excavation was around a 48” sewer main, which ran perpendicular to Darby Creek. The sewer main was approximately 60 years old and carries approximately 14 million gallons of sewage per day. EAT injection grouted underneath and on both sides of the sewer main to stabilize the pipe during excavation.

This project also required extensive restoration, including the following:

      • Construction of a boulder wall on top of bedrock by stacking ½ ton boulders.
      • Restoration of the creek bed
      • Installation of Coir matting
      • Installation of live stakes, various trees, shrubs, plugs and specialty grass mixtures

EAT completed the project to the satisfaction of the Client and property owner.

Who You Choose For Clean-up Matters

See Why Companies Trust Enviro-Air Technologies

Sea Isle City, NJ

Sea Isle City, NJ

Time Frame: September 2013 - May 2014

EAT was contracted to excavate, transport, and dispose of 16,000 tons of MGP impacted soil from 3 residential properties located on the barrier island of Sea Isle City, NJ. The project involved the following:

  • Demolition of 3 residential properties
  • Driving 33,250 square feet of steel sheet piling to create (16) individual excavation cells
  • Excavation dewatering
  • Onsite water treatment and discharge
  • Construction of a 118′ X 164′ temporary enclosure, which utilized two air scrubbers
  • Stabilization of saturated MGP-impacted soil
  • Site Restoration

EAT completed the project on time and with no safety incidents.

Who You Choose For Clean-up Matters

See Why Companies Trust Enviro-Air Technologies

Toms River, NJ

Toms River, NJ

Time Frame: January - June 2016

EAT was contracted to excavate and remove both known and unknown substructures and piping, MGP impacted material and TSCA-level PCB impacted material from an area directly adjacent to an active natural gas facility. This project encompassed several different waste streams that required extensive effort to excavate, manage on site, stockpile, transport and dispose of at multiple treatment/disposal facilities. The known/unknown substructures included a tar holder, USTs, concrete pads, timber piles, abandoned natural gas piping and asbestos wrapped piping. Dewatering and handling/disposal of impacted groundwater was a challenging aspect of this project.
  • Seven (7) waste streams were excavated, segregated and stockpiled on site including:
    • TSCA PCB soil
    • TSCA PCB pipe/debris
    • Low level PCB soil
    • Low level PCB debris
    • MGP soil
    • MGP pipe/debris
    • Clean pipe/metal
  • Excavated, transported and disposed of:
    • 2,500 linear feet of underground piping
    • 500 tons of TSCA PCB impacted soil, piping and debris
    • 5,000 tons of low level PCB impacted soil and debris
    • 800 tons of MGP impacted soil
    • 180,000 gallons of MGP impacted and PCB impacted water
EAT finished the project ahead of schedule.

On time. Every Time.

See Why Companies Trust Enviro-Air Technologies